On Friday, road crews were pouring concrete sidewalks on Main Street. Other work that took place this past week included work on the stone retaining wall by the fire department and school, fine grading agg base in preparation of paving 3rd Avenue SW to West project termini, sub-cutting east of Division Avenue, and pouring sidewalk and pedestrian ramps from 1st Avenue SW to 3rd Avenue NW. This week they will be working on paving from the west termini of the project to 3rd Avenue SW, switching to Phase 3 detour, and beginning the Division Avenue intersection reconstruction. Specific questions regarding work being done in Spring Grove can be directed to Tim Hruska at THruska@whks.com. Updates will also be posted on the project website, www.dot.state.mn.us/d6/projects/hwy44spring-grove/index.html and on the project Facebook page, www.facebook.com/profile.php?id=100003004831362.