This week in Spring Grove, the rest of the sidewalks along Main Street from Division Avenue westward are scheduled to be removed and pouring is to continue at the west end where curb and gutter was set last week and sidewalks are to go in this week.

Also completed last week was the sanitary sewer, water main and storm sewer work between 1st Avenue NW and Division Avenue MnDot reports. Contractors also placed aggregate base from 1st Ave. SW to 1st Ave. NW, did sub cutting from 1st Ave. NW to Division Ave. and poured curb and gutter between 1st Ave. SW and 1st Ave. NW.

Other activities to be worked on this week includes:

• Placing sand and aggregate base from 1st Ave. NW to Division Ave.

• Installing light bases and conduit from 1st Ave. SW to 1st Ave. NW

• Pouring curb and gutter and sidewalk from 1st Ave. SW to 1st Ave. NW

Box culvert replacement continues between Mabel and Highway 52. Watch for local detours.

Updates are will posted on the project website at www.dot.state.mn.us/d6/projects/hwy44spring-grove/index.html and on the project's Facebook page, SpringGroveMnDOT.