Main Street is beginning to look like a real road again as asphalt was laid from 3rd Avenue NW to Division Avenue. Back-filling was also completed from 1st Avenue NE to the Division Avenue intersection. This week plans are to pour the curb and gutter on the east end of the project and prepare for the sidewalk to be poured in this area also. West of Spring Grove paving of the first lift of bituminous from the Underpass Quarry to the west began. Any specific questions regarding the work being done in Spring Grove can be directed to Tim Hruska at THruska@whks.com.